P2P Bridge to close Highway 6 near Tunnel 1
US Highway 6 through Clear Creek Canyon is scheduled to close at 6 p.m. Monday, August 3rd for a period of about 12 hours while a bridge is set in place east of Tunnel 1 over Clear Creek. This is about 1 mile west of the Colorado Highways 93/58 intersection in Golden. Highway 6 will be closed from this intersection to Colorado Highway 119 at the top of the canyon. Drivers will need to take Interstate I-70 to Highway 6 to detour around this closure.
While the highway is closed, a 163-foot-long bridge will be delivered in three sections for onsite assembly. The structure is designed to accommodate pedestrians and cyclists on the Gateway segment of the P2P Clear Creek Canyon Park trail.
The 450 and 500-ton cranes that will lift the bridge will also be erected during this closure. It will take an estimated two hours to place the bridge east of Tunnel 1. Once this is done, the cranes will be removed, the site cleaned up and then Highway 6 can reopen for travel Tuesday morning Aug. 4.
If weather conditions Monday night aren’t conducive, the work it will be rescheduled for Tuesday night.
For additional information about this project, visit the project website at Jeffco.us/p2p.
You can also reach the project team at peaks2plains@gmail.com or 720-893-1313. Please share this information with anyone who might need to know about it.
— By Jefferson County Open Space